News Completion of Riverside RC for March 2020
Contact us

News

06 April 2020

Completion of Riverside RC for March 2020

House № 1
1. Lightning protection device
2. Warming of facade with mineral wool 150 mm thick
3. Facade painting
4. Brick laying of exterior walls on cold transitions 1-7
5. Installation of the frame under the ventilated facade

House №1 p.2
1. Brick laying of exterior walls on cold transitions 1-5
2. Arrangement of input groups

 Improvement between house # 1 and the canal
 1. Backfilling of basement walls
 2. Basement walls insulation
 3. Arrangement of the banks of the canal with reinforced concrete piles
 4. Vertical soil planning for improvement
 5. Arrangement of reinforced concrete piles under the bridge

 
House №2 p.4
1. Installation of glass windows 1-6 floor
2. Installation of window frames 6-7 floor
3. Brick laying of external and internal walls 4-7 floor
4. Installation of monolithic reinforced concrete parapet

House №2 c3
1. Brick laying of external and internal walls 4-7 floors
2. Installation of monolithic reinforced concrete railings

House № 2s2
1. Arrangement of monolithic reinforced concrete pylons and basement walls
2. Installation of the formwork over the basement

House № 2c1
1. Arrangement of reinforcement editions of the vertical elements of the basement
2. Installation of monolithic concrete pylons and basement walls

House № 8 c3
1. Brick laying of external and internal walls 1-2 floors
2. Installation of monolithic reinforced concrete floor 3 floors
3. Arrangement of monolithic reinforced concrete vertical walls 4 floors
4. Arrangement of monolithic reinforced concrete floor 4 floors
5. Installation of monolithic reinforced concrete vertical walls 5 floors

House № 8 c2
1. Installation of monolithic reinforced concrete vertical walls 2 floors
2. Installation of monolithic reinforced concrete floor 2 floors
3. Installation of monolithic reinforced concrete vertical walls 3 floors

House № 8 s1
1. Installation of monolithic reinforced concrete foundations
2. Backfilling of foundations with layer-by-layer sealing of tampons
3. Installation of monolithic reinforced concrete power plate

 
House № 10
1. Arrangement of the pit under the pile field
1. Arrangement of a pile field by pressing fields

  
House № 9
1. Geodetic breakdown of the boundaries for the installation of a ditch
2. Arrangement of the pit under the pile field

Residential quarter of the 1st stage
1. Geodetic layout of the route for the arrangement of external networks
2. Removal of the vegetation layer for the arrangement of external networks
3. Installation of the trough for external networks
4. Storage of pipes of external networks f 225,110,250,400
5. Arrangement of access roads, installation of road plates
6. Dismantling and installation of temporary protection from the construction site decking
7. Installation of concrete pavement for investors