News The performance of the residential complex “Riverside” for November 2019
Contact us

News

17 December 2019

The performance of the residential complex “Riverside” for November 2019

House №1 p.2
1. Installation of the first layer of roof waterproofing
2. Stacking of roofs made of solid brick
3. Lightning protection device
4. Warming of facade with mineral wool 150mm thick
5. Painting the facade

House №1 p.1
1. Arrangement of vertical reinforced concrete structures 7 floors
2. Installation of monolithic reinforced concrete floor 7 floors
3. Arrangement of monolithic reinforced concrete railings
4. Installation of precast blocks 3-5 floors
5. Installation of window frames 5 floor
6. Installation of window frames 6 floor
7. Installation of window windows 1-3 floors
9. Brick laying of exterior and interior walls 6-7 floors

Improvement between house № 1 and the canal
1. Backfilling of basement walls
2. Arrangement of the banks of the canal with reinforced concrete piles
3. Vertical soil planning for improvement
4. Arrangement of reinforced concrete piles under the bridge

House №2 p.4
1. Arrangement of reinforced concrete monolithic sites 1-3 floors
2. Arrangement of vertical reinforced concrete structures 6 floors
3. Arrangement of monolithic reinforced concrete floor 6 floors
4. Brick masonry of exterior and interior walls of 1 floor
5. Brick masonry of exterior and interior walls of 2 floors
6. Brick laying of exterior and interior walls of 3 floors
7. Brick laying of exterior and interior walls 4 floors

House №2 p.3
1. Arrangement of monolithic reinforced concrete floor 3 floors
2. Installation of vertical reinforced concrete structures 5 floors
3. Installation of monolithic reinforced concrete floor 5 floors
4. Arrangement of vertical reinforced concrete structures 6 floors

House № 2 p.2
1. Installation of monolithic reinforced concrete foundations
2. Backfilling of foundations
3. Installation of monolithic reinforced concrete power plate
4. Arrangement of reinforcing releases of the vertical elements of the basement

House № 2 p.1
1. Installation of monolithic reinforced concrete foundations

House № 8 p.3
1. Arrangement of monolithic reinforced concrete foundations of section 2
2. Arrangement of monolithic reinforced concrete foundations of section 3
3. Installation of monolithic reinforced concrete basement walls
4. Arrangement of a monolithic ceiling over the basement
5. Arrangement of vertical monolithic reinforced concrete walls and pylons 1
floor

House № 8 p.2
1. Arrangement of monolithic reinforced concrete foundations of section 2
2. Backfilling of foundations with layer-by-layer sealing of tampons
3. Installation of monolithic reinforced concrete basement walls

House № 8 p.1
1. Arrangement of the foundation pit

House No. 10
1. Installation of test piles
2. Testing piles on load

Residential quarter of the 1st stage
1. Geodetic marking of the route for arrangement of external networks
2. Removal of the vegetation layer under the arrangement of external networks
3. Installation of the trough for external networks
4. Storage of pipes of external networks f 225,110,250,400
5. Arrangement of access roads, installation of road plates
6. Dismantling and installation of temporary fencing of corrugated board
construction site